Update 11th St Construction Project

 

All eyes are on the construction on 11th Street in Coffeyville. The city commission called a special meeting last night to discuss the delays on the project. Superintendent of Engineering Thomas Osborn says they have 105 working days for the project and they have seen a lot of delays due to weather.

 

Osborn says that KDOT is in charge of the project everything has to be approved by them. The City of Coffeyville is only providing 10% of the funding for the project KDOT is providing the other 90%.